施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
县人民医院扩建综合病房楼降水施工方案一、工程概述·································································3
二、周边环境条件····································································3
三、场内工程地质条件····································································3
DB34/T 2727-2016 厂拌沥青混凝土热风式再生工艺规程四、编制依据····································································4
五、降水方案选择·······························································4
六、井点降水相关计算·························································4
七、主要降水设备·······························································5
八、井点施工方法·······························································6
九、工期目标················································7
十、质量标准及质量保证措施································································7
十一、危险点分析···············································8
十二、安全生产及文明施工措施································································8
十三、环保措施················································9
十四、平面布置示意图················································10
工程名称:某县人民医院扩建综合病房楼
建设单位:某县人民医院
本工程位于某县人民医院老院区原儿科病房楼位置,地上12层,无地下室,总建筑面积11874.80m2,柱下桩基础,地上为框架剪力墙结构,建筑总高度49.90m。建筑结构安全等级二级,建筑抗震设防类别乙类,框架抗震等级二级,剪力墙抗震等级一级。
建筑物西侧:围墙(围墙外是泥浆池)
根据山东正元建设工程有限责任公司2010年2月提供的《某县人民医院扩建综合病房楼岩土工程勘察报告》,揭示本场地岩土层结构特征自上而下分层描述如下:
最大厚3.60m,最大深度45.00m
(1)、某县人民医院扩建综合病房楼设计文件
(4)、《建筑施工手册》
(5)、业主提供的周边环境等相关资料
轻型井点据有关文献,理论有效作用半径为:10~15m,井点间距多为1.2m~1.8m,目前,我标所需施工基坑土体多处于第8粉土层,土质渗水率较慢,我公司结合现场实际情况及降水成本问题,从有效降水并节省成本的角度考虑,轻型井点降水的布置:
1、沿基坑四周,底层边桩外约3m布置环状轻型井点。
2、基坑南北面,由于纵深过大,宽度过宽,故在主楼距A轴4.0m处分别布置一排型井点,与沿基坑四周布置的轻型井点形成封闭布置圈。
3、在距楼E轴,A轴4.0m处,距1轴,8轴4.0m处设置形成环闭井点圈,此环井点圈南北面距约26.5m,其工作半径约13.5m;西面距沿基坑四周井点环闭圈约4m,其设计工作半径约为13.5m,东面约为4m其设计工作半径约13.5m。
4、在基础边坡边设环闭轻型井点降水圈,其目的是排降基坑基础下方滞留的地下水,并排除其积水及排除地下基础土体内的地下水。
5、根据以上排布,井点的数量共计为119个,轻型井点设备共计4组。
注:如果现场实际情况与本方案有较大出入时,井点管布管可随时调整。
根据现场水位情况及土质渗透系数,本工程井点管深度按6m考虑(从现场地坪向下埋管),井点工作设计工作半径值为13.5m,为考虑现场实际施工时机械的功率偏差,及不可预见的因素影响,每环轻型井点排降水的工作范围做了小范围的叠加共同工作区考虑,以确保降水的有效性和经济性。
由于基础施工时,轻型井点降水设备在基础施工结束后全数拆除,基础施工时地下水将具有不确定性,故此次轻型井点降水施工不考虑施工期间的天气降水问题,施工时将根据现场实际情况再做考虑。
1、本工程共设轻型潜水泵4台(4.0KW真空吸水泵)。
2、轻型井点降水井点数量为119个。
4、连接排水主管:连接排水主管采用63mmPVC管,与真空吸水泵出水管相连,自排水管节点一端向另一端排向集水井。
4、水位观测孔:现场设水位观测点4个。
5、本工程每组轻型井点设备,连接管、井点管、连接接头均采用直径为25mm的PVC管。
6、集水井:轻型井点真空吸水泵将水排至基坑外集水沟,沿集水沟,每隔约25m设置一个集水井,120mm砖墙砌筑井壁,1:2水泥砂浆内抹灰,集水井底采用C15砼浇筑,厚为150mm,尺寸为:1000mm×1000mm×1000mm(详见平面图),共计:6个。
7、污水泵:出水管径为100mm,置于集水井内,将集水井内的水抽至建设单位指定管网,共计:4个。
布置井点管井点管与总管连接试抽水进入工作状态基础结束及回填完后拔管。
2)、井点管埋设完毕,应接通总管与抽水设备进行试抽水。检查有无漏水,漏气现象,出水是否正常,有无淤塞现象,如有异常情况应及时进行修理。
井点管工作后,应保证连续不断的排水,正常出水规律是“先大后小,先混后清”。如不上水,或水一直较混或出现清后水混等情况,应立即检查纠正。
待基础竣工后,方可拆除井点系统,所留孔洞用砂或土填塞。
因本工程挖土边坡按1:0.33放坡,井点管布置距基坑距离为1.0m,井点管的间距为1.5m。为了减少排水管的数量,降低降水成本,真空吸水泵的出水管直接排入集水沟内,集水沟每25m设置一个集水井,再由污水泵将集水井内的水抽至建设单位指定排水系统。
降水设施完毕后开始降水,降水设水位观测孔4个(深约3m)。观测孔设置于无基础的空白位置,降水过程中随时观测水位并进行记录,发现水位异常随时汇报。降水过程中水泵设备设专人6名昼夜循环进行值班,观测各井点降水情况和各泵运行情况,如下渗水量不满足水泵运行时,及时更换水泵。水位降至基底下0.5米进行挖土施工。
工期目标:降水工期为70天。
质量标准及质量保证措施
过滤器骨架管孔隙率(%)
滤料规格,D50=砂(d50)石(d20)土料含水层倍数
抽排水含砂量(体积比)
(1)、轻型井点、总排水管坐标及高程控制点经基准点引测,检查验收合格后进行布点接管,保证井点坐标位置,及每条排水总管的排水坡度。
(2)、为了保证达到有效降水,机械型号、功率须达到方案要求。
(3)、在施工区域设有降水观察孔,掌握了解降水情况,保证降水效果。
(4)、井点降水设备正常工作后,应设置专人6名24小时不间隔值班,以防出现异常应及时修复。
(5)、开始降水时,应缓慢进行,防止降水速度过快,影响边基坑及周围道路地基发生不均匀沉降;随时观察边基坑及周围道路沉降情况,控制降水速度。
预防措施:根据水泵电机电流量配置相应电源线,做到一闸一机,漏电保护器动作灵活,交接班时对漏电保护器进行试动作,防止因长时间运行而失灵。
预防措施:设置专人巡视基坑边坡的稳定性,防止土方坍塌事故发生。
预防措施:由经考核合格的专业工人进行布点接管施工,有专业执业资格的管理人员进行管理,防止机械伤害。
十二、安全生产及文明施工措施
1、进入施工现场的作业人员,必须正确佩戴安全帽及穿戴好劳动防护用品。
2、如有交叉作业应设专人监护或有防护措施,否则严禁施工,以免发生物体打击及碰撞事故。
3、夜间施工安全照明必须充足。
4、文明施工责任区划分明确,无死角,责任落实,并设有明显标记,便于检查、监督。
5、施工用机械、设备完好、清洁,安全操作规程齐全,操作人员持证上岗,并熟悉机械性能和工作条件。
6、施工现场在施工过程中出现的各种坑、沟、孔洞,应根据实际情况,设置标准的与地平行的安全沟道盖板或可靠的围栏、档脚板或警告标志。
7、拉电源时153 RFJ02-2009 轨道交通工程人民防空设计规范.pdf,严禁将电线直接勾挂在闸刀上或直接插入插座内使用,必须用插头连接。
8、经常组织施工人员进行安全文明施工学习,使每位施工人员掌握安全文明施工知识,不断地提高安全文明施工意识,做到安全生产文明施工。
9、由于井点降水处于湿工作状态下,电源安全装置须达到三级保护要求。
1、井点施工产生的泥浆、弃土应及时清运,运至建设单位指定地点。运输时必须覆盖,避免产生扬尘和遗撒。
2、排出的地下水应经过沉淀处理后方可排入专用管道。
3、施工现场应遵守现行国家标准《建筑施工场界噪声限值》GB12523规定的噪声限值实施性施工组织设计7-28,发现超标应及时采取措施纠正。
井点降水平面布置示意图