0098 某工程模板设计施工方案q1=F×o.33/1000=55.88×0.33/1000=18.44KN/mm
q2=F×0.3/1000=53.5×0.33/1000=17.66Kn/mm
p=0.273×qP4/100E1
=0.273×17.66×6004/100×2.06×26.97×104
DB12T 1166-2022 地面沉降水准测量规范.pdf=1.13mm<[p]=1.5mm(可)
1根Φ48×3.5I=12.19×104mm4W=5.08×103mm3
线荷截q1=F×0.75/1000=55.88×0.6/1000=33.53/mm
q2=F×0.75/1000=53.5×0.6/1000=32.1/mm
330/800=0.41≈0.4
M=0.078×ql2=0.078×33.53×8002=167.38×104N.mm
σ=M/W=167.38×104/5.08×103=329N/mm2
329.5N/mm2>215N/mm2(不可)
方案一、改用两根Φ48×3.5作内钢楞。则抗弯承载能力:
=167.38×104/2×5.08×103=164N/mm2<215n/mm2(可)
方案二、每根内楞间距改为600mm.
M=0.078×33.53×6002=94.15×104/mm
δ=M/w=94.15×104/5.08×103=185N/mm2<215N/mm2(可)
p=0.644×ql4/100EI
=0.644×32.1×8004/100×2.06×105×2×12.9×104
=2.49mm<3mm(可)
c.对拉钢筋Φ12验算
结拉杆的拉力Φ12净面积A=88.74mm2
N=F×0.8×0.6=55.88×0.8×0.6=26.82KN
对拉杆应力δ=N/A=26820/88.74=302N/mm2>215N/mm2(不可)
改不竖向0.3m,纵向0.6m
则N=F×0.3×0.6=10.66KN
δ=10060/88.74=113.36N/mm2<215N/mm2(可)
采用Φ48×3.5钢管支设.取梁断面b×h=250×400,长6000mm的矩形梁.
a.荷载:砼自重24×0.25×0.4×1.2=2.88Kn.m
钢筋荷重1.05×0.25×0.4×1.2=0.18Kn/m
振捣砼荷重2×0.25×1.2=0.6KN/m
合计q1=3.66KN/m
折减系数0.9,则q=q1×0.9=3.29KN/m
底模楞钢间距取0.7,为多跨连续梁,近似单跨计算。
M=q1=3.29×0.7=0.202×10N.mm
=M/W0.202×10/5.08×10=39.76N/mm2<205N/mm2(可)
p=5ql4/384EI=5×3.29×700/384×2.06×105×12.9×104=0.39mm<[p]=I/250=700/250=2.8mm(可)
小楞间距700mm,小楞上的荷载为集中荷载。
取p=q1=3.66KN/m
δ=M/W=0.511×106/5.08×103=101N/mm2<205N/mm2(可)
若取间距900,则δ=130N/mm2<205N/mm2(可)
P=Pl/48EI=3660×103×700/48×2.06×105
×12.9×104=0.2mm<1/250=2.8mm(可)
M=1/10ql2=1/10×3.66×7002=1.8×105N.mm(可)
ó=M/W=1.8×105/5.08×103=35.46M/mm2<205N/mm2
Р=3.66×7002/150EI=1.79×106/150×2.06×105
×12.9×104=0.45mm<1/250=2.8(可)
横杆步距1000mm,立杆允许荷载11.6Kn
YS/T 1294-2019标准下载每根立柱荷载N=19.74/16=1.23KN
立柱稳定验算:ψ=N/ψA≤f
轴心受压稳定系数ψ=0.71
ó=N/ψA=1230/0.7×489=4.75N/mm2<205N/mm2(可)
N=19.74/12=1.65KN
Ψ=N/ψA=1650/0.71×489=4.75N/mm2<205N/mm2(可)
1.剪力墙250mm厚时,选用方案二,内外纵横杆间距600。拉杆选用Φ12公路工程沥青及沥青混合料试验规程(JTG E20-2011)释义手册.pdf,两端与钢模板的U型卡卡牢。
《右营**江东花城模板设计》第8页共8页