宁夏银行办公大厦施工组织方案1.总体概况·······························································2
1.1工程概况·····························································2
1.2工程范围·····························································2
DB43/T 1835-2020 智能轨道快运系统设计规范.pdf1.3工程目标·····························································2
2.施工部署·······························································4
2.1项目经理部组织机构···············································4
3.施工方案·······························································5
3.1施工段划分及主要施工流程······································5
3.2施工重点及难点····················································8
3.3系统施工方案及工艺··············································8
3.4系统调试与试验·················································18
3.5工作界面划分···················································21
3.6现场配合和协调················································23
3.7成品保护措施···················································25
3.8工程投入情况、进场计划·······································25
4.工程进度管理························································25
4.1进度保证措施···················································25
5.安全及文明施工管理···············································26
5.1安全生产管理及措施············································26
5.2文明施工管理···················································29
6.项目文档管理························································30
7.项目竣工验收管理··················································32
7.1到货验收···························································32
7.2初步验收···························································32
7.3试运行······························································33
7.4最终验收···························································33
7.5竣工验收资料······················································34
8.技术培训·····························································35
8.1培训目标····························································35
8.2培训对象···························································36
8.3培训设施及材料··················································36
宁夏银行新建办公大厦位于银川市金凤区北京中路北侧、国家开发银行宁夏分行西侧,占地13.8亩。建筑占地面积14745平方米,总建筑面积41084平方米,其中25层主楼建筑面积25133平方米,4层裙楼建筑面积4741平方米,3层职工餐厅及运动场建筑面积4382平方米,地下车库负一层建筑面积3998平方米。
我公司主要承担一下几个弱电子系统:
⑴综合布线系统(数据、语音)
⑸机房及各弱电设备间系统
我们的最终目标是:满足宁夏银行大厦对各种电子信息系统的基本要求,创造一个信息化、高效、舒适、便利和人性化的环境。
本项目的施工进度计划不仅决定于本系统内部的深化设计、设备安装、调试、试运行和培训所需要的时间,还涉及到土建、机电安装、内外装潢、特殊工艺等施工部门的相应施工进度。
根据现场的实际情况,开工日期为2010年3月25号,竣工日期2010年9月30日,总工期为185天。
根据甲方的要求,我方确定了本工程的施工质量标准的目标为:符合国家智能建筑工程质量验收规范,并通过检验达到合格标准,配合总包确保“西夏杯”,争创“鲁班奖”。
1.3.4文明施工和环境保护目标
我方施工管理按宁夏银川市建设工程施工现场管理办法执行。加强施工组织和现场安全、文明施工管理。
1.3.5现场管理人员基本要求
我方拟定担任本工程施工的项目经理具有国家三级网络工程师资质,曾承担多项类似工程,具有丰富的现场施工管理经验。技术负责人为高级技术人才,从事专业工程多年,具有很强的技术实施能力。现场施工人员均取得了电工职业资格证书,具有很强的现场施工经验。
2.1项目经理部组织机构
项目的组织及团队管理具有如下特点:
银川奥特新技术有限公司针对宁夏银行办公大厦裙楼1,一、三层综合布线工程项目,建立了一套完善的项目组织,为宁夏银行办公大厦弱电系统建设项目提供完善的服务。本公司将委派具有网络工程师资格的有经验的项目经理担任本工程的项目经理,以高效率实现工程项目综合目标为目的,以合同管理为依据,对工程项目进行全过程、全方位的计划、组织、管理、协调与控制。出色地实现质量方针、质量目标以及对业主的承诺。
2.1.1施工管理岗位职责
该项目工程的各个功能组织的职责如下:
项目负责人:负责整个项目的宏观指导,对项目的整体情况负责,有权任命项目经理,以及各项资源的调度和保障。从总体把握整个工程的策划、实施,并有效调配公司的资源,确保工程项目工期及质量等目标的完成。
项目经理:该项目实行项目经理负责制。项目经理负责监督、协调、组织项目合同、项目设计、项目进度计划、配套计划等文件执行,落实施工条件、组织施工队伍、制定切实可行的施工、调度、信息反馈系统,落实设备、材料供应、运输、安装、核算及项目施工等问题,负责全面的质量和管理。
3.1施工段划分及主要施工流程
3.1.1.1深化设计阶段
在本阶段根据总体规划的技术框架,依据总体设计规范、标准,对每个子系统进行详细设计,包括系统具体功能实现、产品选型、实现方式等,形成具体、完整、可实现的施工设计方案。
提供宁夏银行办公大厦裙楼一、三层综合布线工程系统、完整的设计方案,工程预算,以及时间进度计划表。
根据总体设计规范、标准要求,组织不同专业组进行各子系统的深化设计。
深化设计应包含系统组成及功能要求,系统图及系统实现原理,设备选型与配置、实施计划于产品报价。
根据各系统的涉及内容,提出相关专业的配合要求,主要包括如下方面:
与电气(强电)专业配合
根据强电插座分布位置确定相应信息点位
3.1.2.1施工实施程序
根据宁夏银行办公大厦智能化系统工程的施工特点,施工程序可分为施工准备阶段、施工安装阶段、系统调试阶段、工程验收阶段。
3.1.2.2施工准备阶段
这一阶段主要做各种施工准备工作,通过充分细致的准备工作,可为工程施工创造良好的物质和技术条件,是施工能顺利进行的必要保证。我公司将从技术、物资、劳动组织、施工现场和施工场外等各方面做好充分准备。内容主要包括:对图纸的深化设计、熟悉施工现场,编制工程实施总体方案,并采购材料,安排施工人员进场,实施培训。为下一步工程实施做好人力、物力、资料等各方面的准备工作。
3.1.2.3施工安装阶段
各系统施工工作铺开,进入安装高峰期。施工人员、机具、材料进场,各方面的措施都能满足施工要求,现场环境、交叉施工过程中要在规范化管理的基础上采用总体项目施工,结合现场实际情况,实施模块化生产方式。
3.1.2.4系统调试阶段
系统安装完成后进入系统调试阶段,对设备进行通电、调试,线路测通。同时,对于调试方面的细节问题要重视,及时与相关人员联系、协调及给予解决,做好调试记录。
安装调试工作在甲方代表在场时进行;
3.1.2.5工程验收阶段
工程验收分为到货验收、系统初步验收、试运行和系统最终验收四个阶段。
我公司将提供设备原产地出厂证明文件,保证是合同签订后最新出厂的产品。甲方、监理人员与我公司人员在设备到货后共同进行开箱检查,当出现损坏、数量不全或产品不对等问题时,由我方负责解决;
依合同要求对全部设备的型号、规格、数量、外型、包装及资料、文件(如保修单、随箱介质等)的验收。
在整个系统现场安装调试完成后,各方共同按照验收测试计划进行现场验收测试。
系统初步验收后,进行为期1个月的试运行。我方负责解决试运行期间出现的各种故障。在试运行期间,由于设备质量等造成性能指标达不到要求,甲方有权要求我方进行更换或修复,所发生费用有我方负担,且试运行期顺延。
试运行结束后,系统所有性能指标达到技术规格书的要求时,进行系统最终验收,签署系统最终验收文件。
3.3系统施工方案及工艺
3.3.1管槽施工工艺主要控制点及要求
针对本工程的情况特殊、质量要求高等特点,我们针对每个系统施工中的共性及各自特点做到相应的施工技术方案和实施大纲。
3.3.1.1弱电管、线施工标准及要求
严格执行施工规范,按施工图,施工手册进行施工。未经总工签字、项目经理同意并向监理公司申报,不得随意改动施工方案。对施工完成部分要做好成品保护。布管必须横平竖直。
⑴、是不同用途,选用镀锌管线管做线缆护套,镀锌管参照如下方法施工。
金属管因符合设计文件规定,表面不应有穿孔,裂缝和明显的凹凸不平,内壁应光滑,不允许有锈蚀。
现场加工应符合下列要求:
为了防止在穿电缆时划伤电缆,管口应无刺和锐棱角。
为了减少直理管在沉陷时管口处对电缆的剪切力,金属管口应做成喇叭形。
金属管在弯制后,不应有裂缝和明显的凸凹现象。若弯曲程度过大,将减少线管的有效直径,造成穿线困难。
⑶在配管时,应根据实际需要长度对管子进行切割。可使用钢锯、管子切割刀或电动切管机,严禁使用气割。
管子和管子连接,管子和接线盒、配线箱连接,都需要在管子端部套丝。套丝可用管子丝板或电动套丝机。
套完丝后,应随即清扫管口,将管口端面和内壁的毛刺用锉刀锉光,使管口保持光滑,避免破线缆护套。
在敷设金属管时应尽量减少弯头,每根金属管的弯头不宜超过3个,直角弯头不应超过2个,并不应有S弯出现,对于截面较大的电缆不允许有弯头,可采用内径较大的管子或增设拉线盒。
弯曲半径应符合下列要求:
明配管时,一般不小于管外径的6倍;只有一个弯时,可不小于管径的4倍;整排钢管在转弯处,宜完成同心圆形状。
暗配管时,一般不小于管外径的6倍,敷设于地下或混凝土楼板内时,应不小于管外径的10倍。
电线管的弯曲处不应有折皱、陷和裂缝,且弯扁程度不应大于管外径的10%。
金属管连接应牢固,密封良好,两管口应对准。套接的短套管或带螺纹的管接头的长度,不应小于金属管外径的2.2倍。
管接头处应以铜线做可靠连接,以保证电气接地的连续。
金属管连接不宜采取直接对焊的方式。
金属管安设时应符合下列要求:
预埋在墙体中间的金属管内径不宜超过50,楼板中的管内径为15~20MM,直线布管30米处设暗盒。
敷设在混凝土、水泥里的金属管,其地基应坚实平整。
金属管道应有不小于0.1%的排水坡度。
建筑群间的金属管道埋设深度不应小于0.7米;在人行道下面敷设时,不应小于0.5米。
⑺金属管暗设时按下列要求施工:
金属管应用卡子固定,支持点间的距离不应超过3米。在距接线盒0.3处,要用管卡将管子固定。在弯头的地方,两边也要固定。
光缆与电缆同敷设时,应在暗管内预置塑料子管。
当线路名配时,弯曲半径不宜小于管外径的6倍,当两个接线盒间只有一个弯曲时,其弯曲半径不宜小于管外径的4倍。
水平线垂直敷设的明配电线保护管,其水平垂直安装的允许偏差为1.5%,全长偏差不应大于管内径的1/2。
钢管不应有折扁和裂缝,管内应无铁屑及毛刺,切断口应平整、管口应光滑。薄壁电线管的连接必须采用丝扣连接,管道套丝长度不应小于接头长度的1/2,在管接头两端应加跨接地线。
当电线管与设备直接连接时,应将管敷设到设备的接线盒内,当钢管与设备间连接时,应曾设电线保护软管连接,选用软管接头时,不得利用软管金属体作为接地体。
管内穿线钱应将管内积水及杂物清除干净,导线在管内不得有接头,接头应在接线盒内进行,管口处应加塑料护咀,不同回路,不同电压等级、交流和直流的导线不应穿入同根管内。
管线穿在建筑物伸缩缝内,应在伸缩缝两端增加接线盒和接地螺栓。
电缆敷设钱应先核对型号、截面是否与设计相同,进行目测和物理粗侧。
电缆敷设前必须详细勘察放揽现场环境,确定最佳放揽方案。
电缆敷设应根据用电设备位置,在桥架内有里到外整齐排列。
对于使用电缆规格相同的设备,放揽时应先远后近。
电缆固定时,在转弯处弯曲半径不小于电缆直径的6倍。
不放电缆的牵引力,少于电缆允许张力的80%。
对批量购进的四对双绞电缆,应从任何三盘中抽出100米进行电缆电气性能抽样测试。对电缆长度、衰减、近端串扰等几项指标进行测试。
制作电缆头前,根据连接的设备、模块考虑电缆的预留余量。
3.3.1.2模块箱及控制(箱、柜)的安装标准及要求
机柜及设备安装牢固、整齐、美光、端子编号科学易读、用途标志完整,书写正确清楚,设备内主板及接线端口的型号、规格符合设计规定;安装严格按图纸施工、按技术说明书接线;按系统设计图检查主机设备之间的连接电缆型号以及连接方式是否正确,金属外壳接地良好。
3.3.2综合布线系统施工及要求
3.3.2.1配线设备安装
机架安装完毕后,水平垂直度应符合厂家规定。若无厂家规定时,垂直度偏差不应大于3mm。
机架上的各种零件不得脱落或碰坏。各种标志应完整清晰。
安装机架面板,架前应留0.6m空间,机架背面离墙面距离视其型号而定,便于安装和维护。
采用上走线方式时,架顶位置应与梯形桥架下线位置相对应。
应直列垂直倾斜误差应不大于3mm。
接线端子各种接线标志应齐全。
安装机架、配线设备接地体应符合设计要求,并保证良好的电器连接。
3.3.2.2双绞线端接和信息插座的端接
⑴在端接线对之前,首先要整理线缆。
⑵从右到左穿接电缆,并配线架背面的顺序端接线缆。
⑶对每根线缆,切去所需长度的外皮,以便进行线对的端接。
⑷对于每一组连接块,设置线缆通过末端的保护器,这使得线缆对在线缆移动时不变形;
⑸在弯曲线对是,要保持适合的张力,以防损坏单个的线对;
⑹开始把线对按顺序依次放在配线架背面的索引条中,从右到左按配线架背面的色码进行打线;
安装在墙体上的信息插座,应高出地面30CM,固定螺丝需拧紧,不应有松动现象,信息插板应有标签,本系统采用TIA/EIA568B标准接线。
信息插座每孔都有一个8位、8路插线。这种插座的高性能、小尺寸及模块化特点,位设计综合布线提供了灵活性。
从信息插座底盒中拉出约20~30cm;
用环切器或斜口钳从双绞线剥除10cm的外护套;
取出信息模块,根据模块的色标分别把双绞线的四对线缆压到合适的插线槽中;
使用打线工具把线缆压入插槽中,并切断伸出的余揽;
将制作好的信息模块扣入信息面板上,注意模块的上下方向;
将装有信息模块的面板放在墙上,用螺丝固定在底盒上;
为信息插座表上标签,表明序号;
3.3.3有线电视系统
为确保图像清晰,防止干扰,CATV的电缆走向应单独敷设,包括电缆线槽及管线:
有线电视的同轴电缆不得与电力电缆在同一线槽中敷设,或在同一接线箱中安装。
同轴电缆与电力线缆的问距不应小于O3米;
有线电视同轴电缆路由应短直、稳定、安全可靠、便于维修检测,同轴电缆应远离容易受碰击、重压或损伤的场合,尽量减少与其他管线等障碍物交叉跨越的机会。
3.3.4机房及UPS系统施工工艺及要求
根据设计图纸和现场实际情况进行放线,确定房间布局,隔墙位置,应考虑吊顶和地板铺设时的对缝和边板尺寸不能太小。首先划出横向和竖向的基准线。
根据设计图纸划出隔墙位置,根据现场情况可进行尺寸不大的调整,偏差较大时,应通过设计人员和甲方认可,并办理设计更改手续。复核房间的吊顶和地板,边板尺寸不能太小。放线完毕后,必须经复核无误后才可施工。
电气工程施工工艺流程:
线管线槽吊杆、支架安装一一线管、线槽安装——设备支架制作一一电缆、电线敷设一一设备进场检验——线缆绝缘测试——设备就位安装——设备接线——设备调试——设备试运行
所用的钢管应壁厚均匀,无劈裂、无砂眼、无楞刺、无凹陷管,所有钢管预先刷好防锈漆。导线穿线前检查导线是否有背花,绝缘皮损坏现象,并进行绝缘摇测,然后穿线。
管、盒连接紧密,管口光滑,护口齐全,排列安装整齐牢固,管子弯曲处无明显皱折。
管子进入盒(箱)处顺直,在盒(箱)内露出的长度小于5mm。用锁紧螺母固定的管口,管子露出锁紧螺母的螺纹为2~4扣。
管子进盒,位置正确,一孔一管,不得开长孔,严禁用电气焊开孔。
管内导线有适当余量,导线在管子内无接头,导线连接牢固,包扎紧密,绝缘良好,不伤芯线。
盒(箱)内清洁无杂物,导线整齐,护口、螺母齐全、牢固。
管与管、管与盒(箱)接地线截面积正确,防腐的部分涂漆均匀无遗漏。
接地线整齐美观,无虚焊,涂刷后不污染设备和建筑物。
线缆的品种、规格、质量应符合设计要求。
位置正确、固定可靠、油漆完整。
在转弯处能托住电缆平滑均匀的过渡。
托架加盖部分盖板齐全。
管口光滑无毛刺,固定可靠,弯曲处无明显变形现象,弯曲半径符合规范。
电缆敷设严禁有纹拧,压扁,护层断裂和表面划伤等现象。
封闭严密,填料灌注饱满,无气泡,芯线连接紧密,绝缘带包扎紧密,表面光滑,无裂纹。
电缆头安装、固定牢靠、相序正确、标志准确清晰。
导线与电器或端子排的连接紧密,标志清晰、齐全。
二次接线排列整齐,回路编号清晰齐全,每个端子回路上接线不超过两根。
在安装前应对插座盒预先进行处理,(如调正、调平、清扫等)安装时应先检查位置高度与设计要求有无偏差,导线数量是否符合,然后再安装。
同一房间,同一平面高度的插板应水平。高差小于5mm,插座的接线面对插左零右相上接地。
插座安装牢固端正,位置美观正确。
插座的面板应端正、严密并与墙面平;同一室内安装的插座高低差不应大于5mm,成排安装高度应一致,高低差不大于2mm;
各种插座安装牢固,位置准确,接线牢固,标高符合.然后再安装。插座的位置按图中排列,以便维修。
插座的接线严格按照左零右火接线方式连接,不得接错。
并排排列的强弱电插座间距不得小于500mm。
在机房专用空调区域,应做好防尘处理,以保证机房的洁净度。
铲除屋顶悬挂物,有凹陷地方,应用腻子刮平,顶面刷防尘漆。
插吊顶板前,项蓬内的管线、灯具应擦干净后再插吊顶板。
将地面打扫干净,用湿拖布清理2—3遍,保证地面无尘土。
将地面缝隙,清理干净后用密封胶进行密封,防止缝隙起尘。
突起的地方用手砂轮磨平,凹陷地方用水泥压光找平,地面刷防尘漆2—3遍。
待全部设备安装完成后,检查线路敷设和按线全部符合设计图纸要求。各设备按系统检查,进行单机运行正常;与各系统的联动、信息传输和线路敷设满足设计要求。
3.4.2弱电系统工程施工和调试使用的仪表
(2)万用表,有数字式、指针式多种型号,可测电阻、电压、电流。灵敏高,
频率范围广,用于线路测量、系统调试:
(3)摇表。额定电压500V,用来测量和检查线路设备或线路的绝缘电阻。
(4)直流电桥。用来测量精密直流电阻值。
(5)全频电视信号发生器。PD5388A用于线测量和系统调试作信号源用。
(6)场强仪,用于测量电磁场强度。
(7)数字毫伏表。用于测量从低频、高频小电压。
(8)示波器。用于系统调试中测量信号快速变化的波形。
(9)逻辑笔。用于系统调试中测量数字电路或系统中某点的逻辑状态。
(10)电脑(线号+标筌)两用打字机TM一35E,用于打印线路编号。
(12)选频电频表。用于测量传输衰减、串音衰减、放大器的增益、滤波器
(13)简易综合布线测量仪,用于测量UTP双绞线。
系统测试在测试小组开展,在测试环境中实施,由测试经理统一负责。分为系统
测试准备,系统测试实施。测试遵循测试规程进行。
3.4.3调试计划步骤
1)、应用软件测试准备。测试经理测试编制系统计划(包括系统测试的目的、测
试环境、测试范围、测试人员和测试进度安排)和测试用例。1天
2)、检查测试环境,确认测试环境(包括硬件、网络、操作系统、数据库系统软
件、数据库服务器、客户机等)。2小时
3)、原系统典型业务办理,先将系统进行备份,然后在原系统办理若干典型业务,
打印处理结果,各份系统数据;恢复系统到正常状态。4小时
4)、测试实施。新系统测试准备好后,测试经理组织测试人员按照测试计划和测
试规程实施。使用典型业务用例,完成后与原系统的处理结果进行对比。如果完全相
同,则测试通过。2小时
5)、测试问题解决。当测试中发现问题时,测试经理提交《测试问题报告》。组
织有关人员分析后,进行处理。处理完成后,提交处理结果说明。测试经理组织测试
人员对处理结果进行检查,同时进行回归测试,确认所有问题得到解决。回归测试中
发现的问题时,将提交新的测试问题报告。解决的问题将关闭测试问题报告。回归测
试采用同样的测试用例。1小时
6)、测试结束。当系统测试或回归测试问题降低到一定程度时,结束测试,测试
经理提交《测试分析报告》,软件、文档纳入版本管理系统。l天
应用系统的测试和移植保证在要求的时间内完成,所以移植和测试工作并行,准
各和总结工作需要做得充分一些。测试完成进行连续试运行一段时间。
T/CECS 10088-2020 波形梁合金钢护栏(完整清晰正版).pdf建筑智能化系统设计与各专业的配合直接关系到智能建筑工程项目的施工及安装
调试质量,对于系统集成商工程施工和安装调试有较大的影响,甚至影响到工程的进
度和工程的质量。智能建筑安装调试需要各专业设计人员的共同努力。
工作界面的确定是明确各子系统的功能及相应之间接口界面,系统总包商和各子
系统分包商的职责,以确保系统集成成功,否则将会导致系统集成的失败。实质上工
作界面的确定是各系统的纽带普通模板及支撑体系施工方案,柱模、梁模、墙体、楼梯支模安装 108页,集成系统如果没有纽带将变为独立分散的子系统。
工作界面的确定贯彻于设备选型、系统设计、施工、工程管理及系统维护的全部过程,是系统集成的基本保证。
工程接口界面应该标准化、规范化、模块化,这样有助于系统的集成。