施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
某住宅楼6#、7#楼及地下车库17至39轴(B段)施工组织设计基本情况及会签···········································1
工程概况·················································5
施工部署················································11
施工平面布置图··········································13
卸料平台搭设施工方案施工准备工作············································14
主要项目施工方法········································23
质量保证措施············································53
安全技术措施············································57
技术节约措施············································64
冬季施工措施············································66
雨季施工措施············································68
主要材料用量············································70
技术经济指标············································71
附录····················································72
施工组织设计补充········································74
附图一:深基坑挡土支护结构平面示意图
附图二:深基坑挡土支护结构剖面示意图
附图三:降排水系统平面图
附图四:吊模施工示意图
附图五:地下室墙模板支撑图
附图六:外脚手架搭设形式
工程名称:×××6#、7#楼及地下车库17至39轴(B段)
工程地点:××××××
建设单位:××××××
设计单位:××××××
总包单位:××××××
监理公司:××××××
监督单位:××××××
开工时间:××年11月20日
公司部门审核会签(一)
公司部门审核会签(二)
SBS改性沥青卷材防水
现浇混凝土墙,外墙300mm内墙200mm
厚度250mm100mm
SBS改性沥青卷材防水
SBS改性沥青卷材防水
现浇混凝土墙,外墙300mm内墙200mm
厚度250mm100mm
SBS改性沥青卷材防水
SBS改性沥青卷材防水
现浇混凝土墙,外墙300mm内墙200mm
厚度250mm100mm
SBS改性沥青卷材防水
6#楼5.3m、7#楼5.2m
6#楼1.4m、7#楼0.5m
大体积混凝土类型供货单位
预应力混凝土管桩、混凝土方桩
深基坑挡土支护结构平面示意图(详见附图1)
深基坑挡土支护结构立面示意图(详见附图2)
注:用于基坑东侧25m处
建筑红线控制桩坐落位置及示意图
给定水准点高程及位置示意图
设计室外绝对标高(m)
6#楼3.857#3.80
设计首层地面绝对标高(m)
6#楼4.357#4.30
该建筑位于×××地内。建筑南侧为拟建建筑,即×××7#楼;建筑北侧为施工临时道路,建筑西侧距××河仅为30m米,建筑东侧为施工临时道路和拟建建筑,施工现场较平坦开阔。
红线内地下埋藏物及管线状况
本场地原为荒地,局部有坑塘,后经人工填垫至现地坪,现地坪基本平坦。
地下除布满杂填土和部分地区有淤泥外无任何埋藏物及管线。
场地表面局部有击水,地表层-1.4m以下见水,采取拟建建筑物周围明沟及集水井排水,并在基坑平面内纵横间隔20m设管井,井深8米,进行降水。
6、7#楼部分按楼层分段
垂直运输设备类别及数量
水平运输设备类别及数量
以楼层分段,每层一段。
室内装饰以楼层为施工段
门窗安装、外檐涂刷不分段
设备工程配合装修工程进行不分段。
施工准备工作(技术工作准备)
项目经理、工长、技术员
项目经理、工长、技术员
由专人制定JC/T 2137-2012标准下载,交项目经理审核,本着全面准确反映实际工程
施工准备工作(临电一)
确定电源进线、变电室、总配电箱等位置及线路走向;
选择变压器、导线截面和电器类型、规格;
JG/T 537-2018标准下载绘制电气平面图、接线系统图;
制定安全用电技术措施和电气防火墙。