施组设计下载简介:
内容预览随机截取了部分,仅供参考,下载文档齐全完整
金泰广场土钉支护专项施工方案土钉墙方案一编制依据···············································4
㈠施工合同·········································4
市利源针织有限公司施工组织设计㈡施工组织设计·····································4
㈢桩位图、基础平面图·································4
㈣勘察设计文件·····································4
㈤现场踏勘资料·····································4
㈥主要规程与规范···································4
㈦有关地方标准、规程································4
㈧有关企业标准·····································4
二工程概况···············································4
㈠建筑工程概况·····································4
㈡基坑工程概况·····································5
1、基坑概况·······················································5
2、基坑支护设计要求···············································5
3、场地工程地质条件···············································6
4、工期与质量要求················································8
三施工准备··············································8
㈠组织准备·········································8
㈡技术准备·········································8
㈢现场准备·········································9
㈣物资准备········································9
四土钉墙施工·············································9
㈠施工流程···········································9
㈡施工控制要点·······································10
五降水、排水·············································13
㈠施工排水措施·······································13
㈡施工方面采取的措施·································13
六施工监测及应急措施····································14
㈠监测内容··········································14
㈡监测点的设置·······································15
㈢监测次数及方法·····································15
㈣监测数据处理及方法·································15
㈤报警值············································15
㈥应急措施··········································16
㈦深层监测··········································18
1、监测方案依据及内容················································18
2、监测点的埋设及施工监测方法········································18
3、监测精度及所采取的技术措施报警值··································19
4、施工及组织························································20
七施工机械与人员配备····································20
㈠项目经理部人员配备·································20
㈡施工人员的配备·····································21
㈢主要施工机械配备···································21
八工程进度计划与工期保证的组织、经济措施·················21
㈠组织措施··········································21
㈡经济措施··········································22
九质量保证措施和质量通病及预防措施······················26
㈠质量保证措施·······································26
㈡质量通病及预防措施·································28
十安全、环保、文明施工措施································28
㈠安全施工措施·······································28
㈡环保施工措施·······································30
㈢文明施工措施·······································31
十一应提交的交工资料····································32
金泰广场土钉支护专项施工方案
㈢、桩位图、基础平面图;
依据的岩土工程勘查报告为浙江省华夏工程勘察院05年8月提供的《杭州金泰房地产开发有限公司金泰广场区块岩土工程勘察报告》
《基坑土钉支护技术规程》CFCS96:97
㈦、有关地方标准、规程:
企业ISO质量体系管理文件和环境/职业健康安全管理体系文件以及企业项目管理手册等。
①对原材料的技术要求:
②对施工机具的技术要求:
成孔机具:根据施工现场土质情况及环境条件,选择适宜的成孔钻具。如果钻孔时不出水,可用螺旋钻或洛阳铲;若在涌水、涌砂地层中钻孔,可选用冲击式锚杆机或地质钻。
搅拌机:搅拌水泥砂浆时,宜采用强制性搅拌机.
空压机:应分别满足风动成孔钻机和喷射风压的要求.一般选用9m3以上空压机.
输料管:管壁应能承受1.2Mpa以上的压力,并且有良好的耐磨性.
必须遵循施工工艺的要求;必须满足施工方法和施工机械的要求;必须考虑施工组织的要求;必须保证施工质量的要求;必须考虑施工安全的要求;必须考虑当地当时的气候条件.
⑴地形、地貌及环境条件
该工程区在杭嘉湖平原的西南侧边缘,地貌单元属钱塘江冲海积、冲积平原。
根据浙江省华夏工程勘察院提供的工程地质勘察报告,场地内基坑开挖极其影响范围内土层分布如下:
③层;淤泥质粉质黏土,工程力学性质差,属高压缩性软弱土,不宜直接作为基础持力层。
⑤层;黏土,工程力学性质一般,属中偏高压缩性土,不宜直接利用作桩端持力层。
⑦层:粉砂,工程力学性质较好,全场分布,但厚度不大,不宜单独使用。
由于勘探期间正逢干旱与台风期间,地下水位变化较大,测得地下水位埋深在0.60m—3.70m,地下水性质为第四系孔隙水,主要受大气降水补给,水位随季节、气候变化而升降,一般水位年变幅在1.00m—1.50m
基坑土钉墙围护工程计划工期40天。工程质量应确保围护工程结构可靠,基坑边线与标高应符合设计要求和规范,预留工作面应满足土建工程施工需要。
按该工程计划安排,要确保在规定时间内完成下列各项施工准备工作,以便及时开工。
⑴成立项目经理部,建立项目管理机构。
⑵选择技术骨干,组织劳务队及时进场。
项目部人员组成及劳动力需要计划详见附表2、4
⑴根据施工图、地质报告、合同,在开工前完成施工组织设计的编制工作。
⑵认真进行图纸会审,与业主履行必要的围护平面图的审核手续。项目经理应组织技术人员、施工人员,由工程师进行技术交底、施工组织设计交底和施工承包合同交底,进行质量、安全、文明施工教育。
⑶及时进行必要的材料试验。
⑴平整作业场地和临设场地,接通电源、水源。。
⑶放线:与甲方履行正规的测量基准点资料和桩点的交接手续,设置测量控制点,测定围护边线与桩位。控制点应不受施工影响。
⑷摸清施工障碍物,尤其要摸清地下施工障碍物,以便采取措施,防止发生施工事故。
⑸按施工总平面图营建生产临时设施。
⑴落实并组织施工机具进场。
⑵组织货源,按施工进度要求及时进料。
拟配备的主要施工机械与主要材料需用量详见附表1、表3
1、开挖工作面,修整边坡,埋设喷射砼厚度控制标志。
3、钻孔安装土钉、注浆、安设联接件。
工作面开挖应遵循下列原则;
②先开挖道口工作面,待道口土钉完成后再开挖其余部分的工作面。
①土方开挖应与设置土钉相协调,应按设计规定的分层开挖深度(即土钉竖向距离)和设置土钉的施工顺序分段进行。
②为确保工程质量,上层作业面的土钉与混凝土面层未完成不得进行下一层深度的基坑开挖。
土方开挖到基底标高时,应报请监理、联系土建单位进行垫层施工,尽量减少基底土体的暴露时间。
采取任何开挖手段开挖,严禁边壁超挖或松动边壁土体。基坑边壁利用铲锹人工切削修坡,保证边壁平整并符合设计规定的坡度。
④边壁土体暴露时间不得超过规定时限。对于字稳能力差的土体如高含水量的黏性土和无天然黏结力的砂土应立即进行支护。
①喷射混凝土的喷射顺序应自下而上,喷头与受喷面距离宜控制在0.8m—1.5m范围内,射流方向垂直指向喷射面,但在钢筋部位,应先喷填钢筋后方,然后再喷填钢筋前方,防止在钢筋背面出现空隙.
④喷射混凝土强度可用边长100㎜立方体试块进行测定,制作试块时应将试摸底面紧贴边壁,从侧向喷入混凝土,每批至少留取3组试件,每组3块.
①放样:经纬仪、水准仪、钢卷尺测量并编号。
①钢筋调直、除锈、去污。
②尽可能不搭接,用焊接。
④注浆导管与钢筋一起安装。导管端部用2.5m—5.0m用混凝土锚固。
①向孔内注入浆体的充盈系数必须大于1
②注浆用水泥砂浆的水灰比不宜超过0.4—0.45。当用水泥净浆时水灰比不宜超过0.45—0.50,并宜加入适量的速凝剂等外加剂用以促进早凝和控制泌水。
③用于注浆的砂浆强度用70*70*70(㎜)立方体试件经标准养护后测定,每批至少留3组试件,每组3块。
①在喷射混凝土前,面层内的钢筋网片应牢固固定在边壁上并符合规定的保护层厚度要求,一般≥25㎜。
③钢筋网片可用焊接或绑扎而成,网格允许偏差为±10㎜.钢筋网铺设时每边的搭接长度不应小于一个网格边长或200㎜,如为焊接则焊长不小于网筋直径的10倍.
①喷射混凝土的喷射顺序应自下而上,喷头与受喷面距离宜控制在0.8m—1.5m范围内,射流方向垂直指向喷射面,但在钢筋部位,应先喷填钢筋后方,然后再喷填钢筋前方,防止在钢筋背面出现空隙.
④喷射混凝土强度可用边长100㎜立方体试块进行测定,制作试块时应将试摸底面紧贴边壁,从侧向喷入混凝土,每批至少留取3组试件,每组3块.
为了方便施工、保证基坑安全,应采用临时排水措施排除地表水和基坑作业面积水。排水措施包括地表排水,支护内部排水,以及基坑排水,以避免土体处于饱和状态并减轻作用于面层上的静水压力。
⑴地表排水:在基坑外边设置排水沟,使雨水往基坑外流入排水沟内排走。
⑵支护内部排水:在支护面层背部应插入长度为40—60㎝、直径不小于4㎝的排水管,以便将喷射混凝土面层后的积水排出。
在土钉支护工程中,首先要防治水土作用造成的不良影响.目前,在土钉支护工程中采取的措施主要有防、排、堵、挡、抽等方法,同时配合以信息动态施工。
①防,就是预防和防止为主。
②排,就是要对一些水体予以疏导。
③堵,即对部分水体予以封堵,防止渗入或流入基坑。
④挡,修建挡水构筑物以截断水体的径流途径。
⑤抽,即进行基坑降水。
如果针对边坡两种不同的吸水途径及具体的工程、水文、环境特点采取相应的防治措施,如结合施工以上多种办法,并与动态设计信息化施工相结合,及时对出现的异常情况予以解决,事故是完全可以避免的。
②开挖基坑应当按设计步骤和深度进行,严格控制土方分步开挖的高度,并严禁超挖。
③缩短水平方向开挖的分段长度,加快施工节奏以减少暴露时间。
④加强焊接,提高土钉、网体和面板的整洁性。
为确保施工安全和基坑开挖的顺序进行,从围护工程开始施工至地下室底板完工,应进行全过程的施工监测,以便及时掌握施工全过程围护结构、周围土体的受力与变形情况,及时掌握基坑开挖对周围环境、尤其对建筑物、道路的影响程度,以便在监测信息指导下,及时采取有效措施、调整施工方案,避免基坑开挖的重大事故发生,减少事故带来的经济损失和社会影响。
土钉围护的施工监测应包括如下内容:
⑴围护体的位移及沉降;
⑵地表开裂状态及周围环境变形;
⑶基坑渗漏和危及支护安全的水害来源。
⑷基坑底部土体有无隆起,围护外侧土体有无下沉。
⑴监测点、后视点、水准基点应设置在基坑施工影响范围外。
⑵沉降和位移监测点应设在基坑边壁和基坑底部,间距不宜大于30m.
⑶地表开裂,易采用标记法进行观察和比较,有裂缝时,先测量其宽度并做好记录,然后用水泥浆灌实抹平,必要时可拍照留存。
⑴在基坑开挖期间,每天监测次数一次为宜,当位移出现发展趋势或接近预警值时,应加大监测的频率。。
⑵地下室底板完工后可减少监测次数,地下室侧墙完工后停止监测。
监测数应即填入规定的表格,及时向项目经理报告,定期向业主和监理工程师报告。如发现数据明显变化或临近报警值时应即向项目经理、业主、监理工程师报告。
根据设计规定,报警值如下:
⑵其余剖面坡顶水平累计位移60㎜,连续3日位移大于3㎜/d,并且有发展趋势。
⑶地面沉降大于基坑开挖深度的1%。
当位移接近或达到预警值时,或建筑物底部或周围土体出现可能导致剪切破坏的迹象或其他可能影响安全的征兆(如流沙、涌土、隆起、陷落等)时,应立即报警,确定可能采用的应急措施,排除险情。
1、由于基坑施工受各种客观因素的影响,可能会发生各种险情,为能及时排除险情确保安全,应采取如下应急措施;
⑴成立以项目经理为组长的监控小组,在土方开挖和土钉墙施工阶段进行24h监控,监控内容包括:墙体水平位移,土钉墙结构变形,周边土体道路及管线的变化。
⑶当围护体位移超过预警值时,使用砂袋压载,防止支护结构位移的发展。
⑷当支护结构的位移增大时,必须时可使用挖土机迅速回填土方反压,以阻止位移的进一步发展,并在位移处设置超前支护,待稳定后方可继续开挖。
⑸当施工时遇上流沙等土层时,应先打入竖向注浆管进行加固,然后开挖。
2、为了确保安全施工,针对假设出现的几种险情,制订了如下应急措施:
⑴围护体滑移的应急措施
根据监测信息,如发现围护体位移超过容许值,应即采取如下措施阻止位移:
①坑外卸载,具体办法同上相关措施。
②在坑内紧急垒堆砂袋或回填压载。
③位移较大并有发展趋势时,可在坑内设置内撑。内撑可为水平撑或斜撑。可用型钢或坚固的木料支撑。
④必要时可采用增加或加长水平土钉的措施,可酌情在松动的围护体内设置竖向土钉(注浆)。
⑵坑底土体隆起的应急措施
①由于围护体滑移造成的坑内土体隆起,应采取处理围护体滑移的措施,同时用重物(叠袋、回填土)压制隆起土体。
②由于淤泥绕过围护体流向坑内造成的土体隆起,应在坑内利用重力压制隆起土体的同时,对围护体进行加固。设置竖向土体(注浆)加固围护体的有效措施。
⑶周边道路或地下管线破坏的应急措施。
造成周边道路或地下管线破坏的直接原因就是围护结构位移或坑底隆起,因此防止发生此种情况的预防措施是:
①加强施工监测,实行信息化施工。
②发生围护位移或坑内土体隆起时,应即采取措施处理。
①及时查明地下裂缝原因,采取相应措施阻止裂缝的发展。
②及时用浓水泥浆灌缝。
1、监测方案依据及内容
①业主提供之总平面布置图;
②业主提供之综合地下管线图;
③业主提供的基坑围护方案及相关图纸;
④有关相类似基坑信息华施工监测实例。
为了及时收、反馈和分析周围环境和围护结构在施工中的变形信息,实现信息化施工,确保基础施工安全。综合业主提供的资料,基坑围护方案中对施工监测的要求及本工程特点,考虑本监测工程设置以下几方面的监测内容:
①周围地下管线变形(沉降、位移)监测;
②基坑外地下水位监测;
③深层土体位移(测斜)监测;
④围护墙顶变形(沉降、位移)监测。
2、监测点的埋设及施工监测方法
模拟点埋设方法:在地下管线相应上方开挖约30㎝深洞,将顶面刻划“+”的钢筋埋入其中,并用混凝土将其固定;间接点法埋设即直接将顶面刻划“+”的道钉打入地下管线对应上放路面。
测量方法:沉降监测按国家二等水准测量各限差要求进行测量,每次测量宜做到闭合或附合,并符合二等水准的各项精度要求。位移测量采用小角度法。
⑵周围建筑物沉降监测点
埋设:建筑物监测点直接用冲击钻在外墙体上打洞,并将道钉打入或用“L”形钢筋用水泥砂浆固定。
测量方法:同地下管线监测。
⑶基坑外地下水位监测孔
埋设:采用钻孔埋设。将面包裹工业滤网的PVC水管放入钻孔内用中砂回填至密实再用混凝土封口,以免地表水渗入影响观测,水位孔深度均为10.0m。
测量方法:直接量取监测孔内地地下水位距水位管口的距离。
埋设:采用钻孔埋设。在埋设点上用钻孔,到达设计深度后,逐段安放测斜管,顶底封闭,接头处用自攻螺钉拧紧,并用胶布密封。安放完毕后用膨润土及黄砂回填,直至钻也隙密实为止,并用混凝土封口,孔深根据基坑深度确定。测斜管内的十字导槽必须有一组垂直于基坑边线。
测试方法:先以测斜孔底为起测基准,以0.5m点距由下向上进行测试,测试数据处理时均用经纬仪测得的测斜管口的位移值进行测斜成果的修正,经计算处理产生测斜曲线及数据表。
3、监测精度及所采取的技术措施、报警值
①为了确保各项监测项目的精度,投产的仪器必须按规定内容检查标定其主要技术指标,仪器检查合格后方可使用,并做好记录归档。遇特殊情况(受震、受损)随时检查、检定。不合格仪器坚决不能投产使用。
②水准测量宜采用闭合或附合路线观测方法。
③尽量做到测量定人,定仪器;观测数据不得随意涂改,测量数据有疑问时,因做至反复观测寻找问题的原因。
④各监测项目变形量或测量值接近或到达报警值时,应及时发出预警报告或报警,并提请业主及有关单位注意。
①地下管线监测报警值由专业管线公司给定,具体报警值为累计变量≥±10㎜GTCC-010-2020 受电弓碳滑板-铁路专用产品质量监督抽查检验实施细则.pdf,日变量≥±3㎜。
②其他有关监测内容报警值敬请设计单位确定,一经确定,我司将严格按照标准执行。
地下室结构至±0.00其间,地下管线变形监测1次/3d、基坑外地下水位监测次/3d、深层土体位移监测1次/3d、围护墙顶面变形监测1次/3d。
为确保按合同工期完工,应配备足够的施工机械和人员。
成立项目经理部,由项目经理部组织工人员进行履行经营。
劳务队由本公司技术精、作风过硬的生产骨干组成。劳务队人员施工高峰时24人。
配备施工机械应本着满足工期和适应工程特点的需要。
合肥卡迪尔化妆品公司生产车间工程填充墙施工方案.doc八工程进度计划与工期保证的组织、经济措施
1、公司的准备配备装饰施工经验丰富、技术实力强的项目管理班子,中标后立即可投入人力、物力,及时进场组织施工。